Download Free E-book
Direct Toegang
X
Download Free E-book
50% Complete
Download our FREE Guide "Top12 Strategies For The Successful Solar Module Buyer"

Page content

PID & LID: Devastating Phenomena for PV plants

article content

PID & LID: Devastating Phenomena for PV plants

PID & LID - two different kinds of Induced Degradation of PV modules. In the first case Potential Induced Degradation (PID) conducted by high voltages, and the other Light Induced Degradation (LID) conducted by sunlight (real or simulated).

The purpose of this article is not to extendedly describe the micro-scale source of these phenomena, but, some real consequences at the MW scale PV plants, considering the basis of a PV project – the simulation by software.

LID - Light Induced Degradation

Silicon PV modules have a natural degradation due to the physical reactions (electrons flow) through the p-n junctions of a PV module. Nevertheless, a concept of (initial) "Power Stabilization" should more widely be used, recognized and taken into account.

"Power Stabilization" is an initial degradation occured when modules are exposed to sunlight. The average percentage of power loss for the first year is usually advertised (in manufacturer's datasheets) to be arround 3%.

"Power Degradation" is nowadays advertised to be around 0,8% for the following years, i.e., after the so called "Power Stabilization".

The graphic below summarizes the deviation of Power (Pmpp) of Mono-crystalline and Poly-crystalline PV modules (a total of 58 modules, different brands) relative to manufacturer's data. The test was done to new modules, exposed to real sunlight 25 kWh/m^2 (which means 3 days according to testing site, south of Portugal). After the irradiation exposure, modules where subjected to Maximum Power Determination under STC conditions.

Solar panel Light Induced Degradation LID graph

Effects of Light Induced Degradation (LID): Around 57% of the tested modules showed a power loss of more than 3% (as intended to be the power degradation for the first year of operation). Note that these results were obtained after (only) 3 days of sun exposure.

 

PID - Potential Induced Degradation

PID usually occurs when modules are in strings operating at high voltages (near 1000 V, but not only), combined with very warm and humid weather. Dust and glass degradation (releasing Sodium ions) may catalyse the PID phenomenon.

PID affected modules (often from the negative pole side of a string) usually have a pattern of "black" cells, i.e., cells that were shut down closer to the frame of the module. This pattern has to be with the flow of negative charges, due to the excess of positive charges.

There is an IEC standard (yet in Draft stage) that aims to test the resistance of PV modules to withstand PID phenomenon. Basically one of methods consist is subjecting PV modules to ±1000 V (DC) inside a climate chamber at 85% rH and 60 ºC, for 96h. The graph shows the Pmpp and Electroluminescence images, before and after the 96h test.

Solar panel PID stress test graph

Solar panel PID stress test graph

The result showed above means a power loss about 25% after the 96 hours PID stress test. The "Pass" criteria defined at IEC PID standard states that power loss cannot be above 5% between initial and final measurements. Although this result is relatively to 1 module, it's representative of dozens of PID tests done by the same laboratory to different modules.

 

Project of a 10 MW PV plant case study – at Ahmedabad

Let's consider some assumptions to facilitate the approach:

  • 10 MW PV plant at Ahmedabad;
  • Feed in Tariff (FiT) Rate INR 5,4/ kWh ;
  • Energy forecast performed by "software" (avoiding advertisements, it's a PV project software used globally), using three methods:
    • a) modules parameters according to manufacturer data;
    • b) modules parameters according to real/measured values on a PV laboratory;
    • c) modules parameters acc. to manufacturer data, but filling the options "Module Quality - LID - Mismatch" at the "Detailed losses" software window;
  • LID mismatch of 5,5 %;
  • PID effect resulting on a deviation of 25 % relatively to the initial measurements.
PV plant Losses Diagrams

PV plant Losses Diagrams

The three simulations were done using 250 Wp rated modules, with 11 MW of installed capacity, limited to the grid at 10 MW. PID usually doesn't occur at the first year of operation, although; let's assume a total mismatch (due to the two phenomena) of 30,5 % - the worst scenario.

A very optimistic result is obtained by making use of manufacturer's data. Although, replacing the PV module parameters (at "software" modules database) by the real values measured on a Solar Simulator, the amount of energy injected into the grid is less 36,2 % (comparing with the manufacturer’s data)For the case of simulation c), making use of "software" alghoritm, and filling the LID and deviation relatively to manufacturer's data (I used this one for PID effect), the amount of energy injected into the grid is effectively less 30,5 % comparing to the manufacturer's data simulation.

 

10 MW PV plant Capital Losses – case study for UK, US, India and South Africa

Picking up the same assumptions and performing a different assessment but more realistic; simulation results will be closer to the reality. So, for the next scenario these are the assumptions:

  • Two simulations, one based on real/ measured data, and the other, based on manufacturer data;
  • For the “real/ measured data” simulation, the assumption is that from the beginning there’s a LID loss of 5,5 % from the beginning, a yearly degradation of 1 % and PID will affect modules at the “Year 3” by 12 % loss of power relatively to the previous year;
  • For the “manufacturer data”, no LID loss was considered, except a power degradation of 0,7 %/year, and no PID effect;
  • Fit or PPA rate assumed are the closest possible as the last auction s in each country.

According to some emerging PV markets, specific locations were selected auch as:

  • Ahmedabad – India
  • Columbia – South Carolina (US)
  • Kimberley – South Africa
  • Exeter – United Kingdom

Results couldn’t be more expressive.

PID and LID effects on pv plant in Ahmedabad

PID and LID effects on pv plant in Ahmedabad

PID LID effects in pv plant in Columbia

PID LID effects in pv plant in Columbia

PID LID effects on pv plant in Kimberley South Africa

PID LID effects on pv plant in Kimberley South Afric

PID LID effects on pv plant in Exeter UK

PID LID effects on pv plant in Exeter UK

 

Concluding...

One of the main goals of this text is to warn for two "issues" that can have a strong influence at the performance of a PV plant.

Most of the project developers and investors are aware of Potential Induced Degradation (PID) and Light Induced Degradation (LID) mismatch, but how to quantify their effect on the phase of a PV plant project?

Another goal is to alert for inaccurate energy forecasts. Taking into account that majority of softwares have already specific tools where the user can fill with the percentage of deviations relatively to manufacturer's data, there's nothing better than consider real/measured values such as Pmpp, Voc, Isc, Impp, Isc, Eff., etc... but also Temperature Coefficients play a crucial role, as well as others.

Last, but not the least, and regarding an accurate/ inaccurate PV project, there is a huge difference between considering the Yearly Power degradation, and Yearly Energy degradation. The effective Pmpp difference at the beginning of operation is arround 4,8%, which leads to a difference of energy production arround 5,7% and 6,5%. It shall not be considered that Yearly Power degradation has an equal percentage of Yearly Energy degradation.

Comment Section

One thought on “PID & LID: Devastating Phenomena for PV plants


By Evsei Berman on 10 May 2017

Very clear explanation on simple way.
Unfortunately so many PV plant owners not familiar with this problem. As well I suggest to add material for PID repairing.

Leave a Reply


*


Hugo Silva
About guest blogger Hugo Silva:Hugo is currently leading the business development of a PV laboratory, based in Portugal providing services worldwide. His career has started as a Physics and Chemistry teacher, when the passion for renewable energies was born a decade ago. Since then, he has been related to renewables business areas, focused on technical rigour to achieve client’s satisfaction. Connect with Hugo on LinkedIn or visit his personal website